Florida Residential Energy Code Forms for New Construction

Beyond the underlying compliance calculation — whether R402 prescriptive or R405 performance — Florida requires specific standardized forms to accompany a new construction permit submittal. These forms exist to give plan reviewers a consistent, predictable format for checking compliance information, and missing or incorrectly completed forms are a common, avoidable reason a permit submittal gets held up even when the underlying compliance calculation itself is sound.

July 22, 2026

Why Standardized Forms Matter

Florida's energy code forms provide a consistent structure for presenting compliance information regardless of which software or method was used to generate the underlying calculation. This standardization is what allows plan reviewers across different jurisdictions to check submittals efficiently, since the key figures appear in the same place and format on every form, rather than varying by whichever report format a given software package happens to produce.

Core Forms for New Construction

New residential construction in Florida typically requires a completed compliance form summarizing the project's chosen path (R402 or R405) along with the key envelope, mechanical, and — where applicable — duct system figures that demonstrate compliance. The specific form used depends on which compliance path was selected, since prescriptive and performance submittals present different information.

Forms Specific to the Performance (R405) Path

Because R405 relies on whole-building modeling, its associated forms typically need to show the modeled design's performance relative to the baseline, along with the specific mechanical and duct system assumptions used in the model — details that a prescriptive submittal's forms don't need to include in the same depth.

Common Form-Completion Mistakes

The most frequent issues are incomplete fields left blank rather than filled with the applicable project data, using an outdated version of a form after an update to the state's requirements, and forms that don't match the accompanying compliance calculation — for example, a form indicating R402 prescriptive compliance while the attached documentation reflects an R405 performance calculation.

Confirming Current Form Versions and Local Requirements

Florida's energy code forms are updated periodically alongside code cycle changes, so using a current version — rather than one saved from a previous project — matters more than it might seem. Some local jurisdictions also require supplemental forms beyond the state minimum, which is worth confirming before assembling a final submittal package.

R405 Checklist: Core Modeling Documentation

At the center of an R405 submittal is the energy modeling report itself, generated through an approved software tool, showing that the proposed design's total energy performance meets or exceeds the code baseline. This report needs to reflect the actual proposed building — envelope specs, window performance, mechanical equipment, and duct system characteristics — rather than generic or placeholder inputs.

R405 Checklist: Envelope and Window Specifications

The submittal needs insulation R-values for walls, roof/ceiling, and floor assemblies, along with window and door U-factor and SHGC data, matching what's shown on the architectural plans. Since Florida's climate places significant weight on cooling load and solar heat gain, window SHGC data in particular needs to be accurate and current, not an early design-phase placeholder.

R405 Checklist: Mechanical Equipment and Duct System Data

R405 modeling incorporates HVAC equipment efficiency and duct system characteristics, including anticipated duct leakage. This means the submittal needs to reflect the actual specified equipment and duct design — often informed by Manual J, S, and D reports — rather than a default assumption that may not match what's ultimately installed.

R405 Checklist: Duct Leakage Testing Commitment

Because R405 compliance frequently claims a specific duct leakage performance target, the documentation package typically needs to reference the field verification process that will confirm that target is met — tying the permit-stage modeling to the post-installation testing that validates it before final approval.

Frequently Asked Questions

Do the required forms differ between R402 and R405 compliance paths?

Yes — R405's performance-based approach requires forms showing modeled performance and system assumptions that a straightforward R402 prescriptive submittal doesn't need to the same degree.

How often do Florida's energy code forms get updated?

They're periodically revised alongside code cycle updates, so it's worth confirming the current version is being used rather than reusing a form saved from an earlier project.

What's the most common reason forms cause a permit delay?

Incomplete fields or a mismatch between the form's stated compliance path and the actual attached compliance documentation are the most frequent, easily avoidable issues.

Is R405 documentation more extensive than the prescriptive R402 path?

Generally yes — because R405 relies on whole-building modeling rather than fixed component checklists, the documentation package needs to show modeling inputs and assumptions in more detail than a straightforward prescriptive submittal.

Does R405 documentation need to reference duct leakage testing specifically?

In most cases, yes, since R405 compliance commonly relies on a claimed duct leakage performance level that needs to be verified in the field before final approval.

What's the most commonly missing item in Florida R405 submittals?

Current, project-specific window SHGC data and mechanical equipment specs are common gaps, since these are sometimes left at early-design placeholder values rather than updated to match the final specified products.

Psychro.Pro prepares complete, current Florida energy code compliance packages — calculation and forms together — checked for consistency before submittal. See our Florida R405 reports.